Researched UK figures for how long it takes, written for homeowners rather than the trade.
Ask a fitter how long it takes and they will say a week. Ask a kitchen showroom and they will say two months. Both answers are honest, and they are answering different questions. How long does it take to fit a kitchen depends entirely on whether you mean the days someone is in your house with a drill, or the whole stretch from the first measure-up to the last bit of sealant.
Fitting a kitchen takes 3 to 10 days on site, depending on the number of units. The full project, from survey to finished room, typically runs 4 to 8 weeks. Most of that is waiting: 4 to 8 weeks of lead time on the units, and 5 to 10 days for stone worktops to be fabricated after templating.
How Long It Takes to Fit a Kitchen, Start to Finish
There are two numbers, and mixing them up is the reason kitchen timelines feel dishonest.
On site, fitting takes 3 to 10 days. That is the fitter, the trades and the mess. Most guides put a typical installation at 5 to 10 days.
Start to finish, the project takes 4 to 8 weeks. That covers the survey, the order, the wait for delivery, the strip-out, the fit, then the worktop return visit and the finishing. On a premium kitchen with a stone worktop, 6 to 8 weeks is realistic.
Other sources put the average at 2 to 6 weeks, and a simple swap can land closer to 1 to 2 weeks. A small kitchen with no structural work might take 5 to 6 weeks from the very start.
The difference between the two numbers is almost entirely waiting rather than working. Nobody is in your house for six weeks. They are in your house for about one of them.
Fitting Days by Kitchen Size
Unit count is what sets the number of days on site. Room size matters far less.
- Small kitchen, 8 to 12 units: 3 to 4 days.
- Medium kitchen, 13 to 20 units: 4 to 6 days.
- Large kitchen, 21 units or more: 6 to 10 days.
Count your own units before you ask anyone for a timeline. It gets you a much better answer than describing the room, because a galley kitchen crammed with twenty units is a longer job than an airy open-plan room with twelve.
These figures assume the layout stays put. Move the sink, the hob or the waste and you add trade days on both sides of the install, because the plumbing and electrics have to be run before the units go in and connected after.
The Five Phases of a Kitchen Project
A kitchen project breaks into five blocks. Only one of them involves anyone in your house with tools.
Phase 1, design and planning: 2 to 4 weeks. Finalising the layout, the units and the appliances. This phase takes as long as you take.
Phase 2, ordering and lead time: 4 to 8 weeks. The longest block, and the one you cannot speed up once the order is placed. A pre-installation survey is usually booked 1 to 2 weeks from ordering.
Phase 3, preparation: 1 to 2 weeks. The old kitchen comes out and any first-fix work happens. A first-fix plumber typically attends 1 to 2 days before installation.
Phase 4, installation: 1 to 2 weeks. The units arrive and the fitter starts.
Phase 5, final fit and finishing: 2 to 5 days. Worktops returning, appliances connected, sealant, handles and snagging.
Written out like that, the shape of the project becomes obvious. Phase 2 is more than half your calendar, and it happens before anyone picks up a tool.
Why Ordering Takes Longer Than Fitting
The date you place the order matters more to your finish date than the fitter's diary does.
German kitchen brands like Nobilia, Ballerina and Bauformat typically carry a 4 to 8 week lead time. Other suppliers may be quicker, especially on rigid carcasses, but a 4 to 6 week wait is normal for painted-to-order ranges.
This catches people out in a specific way. They book a fitter for a date that suits them, then order the kitchen afterwards, and the units arrive two weeks after the fitter was due. The fitter moves on to the next job, and you wait again for a gap in their diary.
Order first, then book the fitter around the confirmed delivery date. If your fitter is worth having, they are busy, so give them a date you can actually meet.
One more thing worth asking the supplier: whether the order is delivered complete or in parts. A kitchen that turns up missing three units is not a kitchen you can fit, and a partial delivery can cost you a week.
Worktops: the Gap in the Middle of the Job
Stone worktops create a pause that almost nobody plans for, and it is the single most common reason a kitchen feels like it is taking forever.
Quartz and granite cannot be cut in advance. The units have to be installed first, then the worktop is templated in your home, measured precisely against what is actually there. Only then does it go off to be made.
That fabrication takes 5 to 10 days. Some suppliers quote 1 to 2 weeks. During that time your units are in, your worktop is not, and you have no sink.
Laminate is different. It can usually be cut on site as the units go in, which removes the gap entirely. If speed matters more to you than the finish, that single choice can take a week and a half out of your project.
Glass splashbacks work the same way and are often worse, at 7 to 10 days for fabrication, sometimes longer for specialist finishes. Tiling, by contrast, is 1 to 2 days.
Plan for the gap rather than fighting it. A temporary sink arrangement and a kettle somewhere else in the house makes that fortnight a great deal easier.
What Makes It Take Longer to Fit a Kitchen
Three things reliably add days, and only one of them is about the kitchen you chose.
Moving services. Relocating the sink, hob or waste means new pipe and cable runs before the units go in. It also usually means plastering afterwards.
Drying time. Plastering takes 1 to 3 days plus drying, and nothing can be fixed to a wall that is still wet. Plastering and flooring together can run up to 5 days. This is dead time that no amount of paying extra will compress.
Flat-pack units. Assembling flat-pack adds roughly 1 to 2 days compared with pre-assembled rigid units. The units are cheaper, and the fitter's time is not, so the saving is smaller than it looks.
Other common delays sit around the edges of the job. Old flooring that fights coming up adds 1 to 2 days. Tiling and decorating at the end takes 2 to 5 days. Unit fitting itself is 3 to 8 days depending on how bespoke the installation is.
Older houses simply take longer. Walls that are not square and floors that are not level turn a straightforward install into a series of small problems, each costing an hour.
The One Day Kitchen: What Is Actually Possible
The honest answer is that a full kitchen cannot be fitted in one day, and any quote saying otherwise is describing a different job.
What can be done in a day or so is a replacement of doors and drawer fronts, sometimes with a new worktop. The carcasses stay where they are. That is a genuine service, it transforms how a kitchen looks, and it is quick precisely because nothing is being taken out.
A strip-out alone takes about a day. Fitting the units takes 3 to 8 days on its own. Adding those together tells you why the smallest realistic full installation is 3 to 4 days, and that assumes rigid units, a laminate worktop and no services moving.
If someone offers you a full kitchen in a day, ask which parts are not being replaced. There will be an answer, and it is usually the carcasses.
Living Without a Kitchen While the Work Runs
The part of the timeline that actually affects you is not the project length. It is the stretch with no sink and no cooker, and that is shorter than people fear.
Real disruption usually runs 1 to 2 weeks. It starts on strip-out day and ends when the worktop is in and the appliances are connected. Everything before that is waiting for a delivery, and you keep your old kitchen the whole time.
A few things make that fortnight much easier. Set up a temporary washing-up point somewhere with a tap, a bathroom or a utility room will do. Move the kettle, the microwave and the toaster into another room before the strip-out rather than during it. Empty the cupboards a day early, because a fitter waiting for you to clear a wall unit is a fitter you are paying to stand still.
Ask your fitter for the running order at the start. Knowing which day the water goes off, and which day the worktop template happens, lets you plan around the two days that matter instead of the whole month.
FAQ
How Long Does It Take to Fit a Kitchen?
Fitting takes 3 to 10 days on site, depending on unit count. A small kitchen of 8 to 12 units takes 3 to 4 days, a medium kitchen of 13 to 20 units takes 4 to 6 days, and a large kitchen of 21 or more units takes 6 to 10 days.
Can a Kitchen Be Fitted in One Day?
Not a full one. A day is enough for a door and drawer front replacement, where the existing carcasses stay in place. A complete installation needs 3 to 4 days at the very least, since a strip-out alone takes about a day and unit fitting runs 3 to 8 days.
How Long Will I Be Without a Kitchen?
Usually 1 to 2 weeks of real disruption, not the full project length. The units go in over several days, then stone worktops take 5 to 10 days to fabricate after templating, which is when you have no sink. Laminate worktops remove that gap.
Does Flat-pack Take Longer to Fit Than Rigid Units?
Yes. Assembling flat-pack cabinets adds roughly 1 to 2 days compared with pre-assembled rigid units. Since you pay the fitter for those days, some of what you saved on the units goes back out in labour. On a large kitchen the difference is worth pricing before you decide.
How Far in Advance Should I Order My Kitchen?
Order 4 to 8 weeks before you want work to start, and longer for German ranges like Nobilia or Bauformat. A pre-installation survey is usually booked 1 to 2 weeks after ordering. Book the fitter only once you have a confirmed delivery date, not before.
Verdict on Kitchen Installation Timescales
Hold two numbers in your head and the whole thing makes sense. Someone will be working in your house for 3 to 10 days. The project will take 4 to 8 weeks. The gap between them is lead time and worktop fabrication, and neither is anyone dragging their feet.
Plan around the waiting rather than the working. Order early, pick laminate if speed matters more than stone, and keep the layout if it already works. Then ask your fitter for a day count rather than a finish date, because how long does it take to fit a kitchen has a straight answer, while how long the whole project takes depends mostly on decisions you make before anyone arrives.
Kitchen Fitters Croydon is not affiliated with, endorsed by, or an approved installer for Wickes, Howdens, Wren, B&Q, IKEA, Magnet or any other kitchen retailer. Retailer names are used only to describe the kinds of kitchen that local fitters install.
Want a Croydon-specific figure? Get quotes from local fitters.